Moving home & installation

How long does broadband installation take?

How long does broadband installation take?

The short answer: it depends which situation you're in

There's no single answer to "how long does broadband take?". The wait depends mostly on what's already in your home, not on which deal you pick. Every order falls into one of four situations:

  1. A working connection is already in the home. It just needs switching on, often remotely, so the wait can be days rather than weeks.
  2. Full fibre has never been installed at the property. Full fibre means a fibre optic cable all the way into your home rather than copper for the last stretch. A first-time install needs an engineer, sometimes after a survey or outside work.
  3. There's no line at all, or it's a new build or a flat. Building work or permissions may be needed first.
  4. You're using a 4G or 5G home broadband hub. Nothing is installed: the hub is posted out and you plug it in.

Below we take each situation in turn, then set out what providers publish about timings, what happens on go-live day and what you're owed if the date slips. Provider timings come from their own pages, checked October 2026. They're what each provider says, not guarantees, so check again before you order.

Situation 1: a working connection is already in the home

If the property already has a working line or full fibre box, the new provider can often activate it from its end. Providers that say so include:

  • EE connects remotely where the home already has full fibre with working Openreach equipment: the hub arrives in the post and you plug it in on your start date.
  • Plusnet says an existing full fibre connection is activated remotely, usually in 3 working days.
  • Sky says that with an active line no engineer is needed and you plug in the Sky Hub on your activation date.
  • Hyperoptic says that if a router and socket are already installed you can get online in minutes.
  • Gigaclear says homes already connected to its network can be up and running within 7 days using its self-install guide.
  • Rebel says you can be live within 5 days if an Openreach or CityFibre line is already in the home.
  • Virgin Media says homes that have had its service before can usually self-install with its QuickStart kit, while homes never connected to its network typically need an engineer to run a cable.

If you're switching provider at the same address, Ofcom's One Touch Switch process applies. Since 12 September 2024 you contact only your new provider, and the switch happens on the date you agree. Any loss of service must not exceed one working day where technically possible, and your old provider keeps supplying you until the new service is active.

If the last occupant's broadband is still active, see our guide on what to do when the previous occupant's broadband is still connected.

Situation 2: full fibre has never been installed

If your home has never had full fibre, an engineer needs to bring a new fibre cable in from the street. On Openreach's network your broadband provider manages the appointment. Openreach says it doesn't have access to your order details, so contact your provider first; the provider will get in touch with Openreach if needed.

The Openreach installation, stage by stage

  1. You order. Your provider agrees an installation date with you. EE, for example, says you choose the date when you order.
  2. Confirmation. You then get texts or emails from your provider or Openreach confirming the appointment, and you can change the date by following those messages.
  3. A possible pre-visit. Openreach sometimes checks the network is ready first, for example by inspecting nearby underground cables or checking whether a telegraph pole can take a new fibre line. You usually don't need to be in. Ahead of the engineer visit you may also get a text from Openreach's partner VYN inviting you to do a short video survey of your home.
  4. Install date confirmed after pre-visit checks. Openreach says it confirms your installation appointment once checks and preparation are done, in most cases a few days after the pre-visit.
  5. Outside work. Openreach may complete some external work before your installation date and will tell you if it does.
  6. Installation day. The engineer runs fibre from an underground duct or overhead pole, brings it through a small hole drilled in the wall and fits an ONT (optical network terminal, the small box your provider's router plugs into). Openreach's help page says most installations take between one and four hours; its installation checklist says an install usually takes around four hours.
  7. Occasionally, a return visit. In a small number of cases the work is more complex and Openreach comes back another day to finish.

Other providers and networks describe a survey or preparation visit before the main install too, including Zen, Gigaclear, Truespeed and Airband (see the table below). For more on the visit itself, read our guide to what to expect from a full fibre installation.

Situation 3: no line, a new build or a block of flats

Here waits are least predictable and firm numbers are scarce. Openreach says most providers need the connection to be ready before they'll accept an order, and that a home with no existing line may need installation work first. Your provider checks this and arranges it.

  • New builds. Openreach says new-build homes typically come with full fibre and an ONT already fitted, so once the network is ready you plug in a router, usually without an engineer. That depends on the developer having arranged it: Openreach asks developers to register sites at least eight weeks before building starts and/or six months before broadband is wanted at the first home. TalkTalk's moving-home help also warns that newly built or converted homes can see delays because cabling may be needed and local council permission can add time. See our guide to broadband in a new-build home.
  • Flats. To bring fibre into a block, Openreach needs a wayleave (formal permission) from the freeholder or managing agent. Its guidance for blocks of flats says that after the wayleave is signed, the process from survey to completion can take several months because these installations are complex. See our guides to full fibre in flats and wayleaves.
  • A home with no line at all. Few providers publish a figure for this. POP Telecom's terms say a new line takes about 4 weeks; treat that as one provider's estimate rather than a rule, and ask your chosen provider what applies at your address.

Situation 4: a 4G or 5G home broadband hub

Mobile home broadband uses a router with a SIM card that connects to a mobile network, so nothing is installed. Three, for example, says its 4G and 5G hubs need no engineer visit and are delivered the next working day. That makes a hub a handy stop-gap while you wait for a fixed line. Whether it could replace fixed broadband for good is covered in our guide on whether 4G or 5G can replace home broadband.

What providers say about lead times

We read each provider's help pages, sign-up pages and terms in October 2026. Where we found no figure, the table says "not found on pages checked" rather than guessing. That doesn't mean the provider never gives one, so ask when you order.

Provider

Connection already in place

New installation needed

Other details

EE

Remote connection where working Openreach full fibre equipment is in place; plug the hub in on your start date

Openreach visit of up to three hours

Most orders live within a couple of weeks; the engineer date is your go-live date

Plusnet

Activated remotely, usually in 3 working days

Usually 3-10 working days

A survey may be needed

Sky

No engineer; plug in the Sky Hub on your activation date

Openreach installs; no lead time in days found

 

Zen

No figure in days on the page we checked

Most full fibre installs completed in 6-20 working days

One or two visits; the first, if needed, is an external survey

Hyperoptic

Online in minutes if a router and socket are already installed

Can often install as early as the next day

Installs six days a week; most visits take one to three hours

Gigaclear

Self-install, up and running within 7 days

Book 14 to 90 days after ordering; dates typically within around three weeks

Outside work first; install visit around 2 hours

Quickline

Not found on pages checked

Usually three to four weeks after ordering where the network is live

Terms: full fibre appointments from 10 working days ahead, fixed wireless from 15

Trooli

Not found on pages checked

Usually within 2 weeks of ordering

Aims for a maximum of 4-6 weeks where possible

Airband

Not found on pages checked

Typically up to three weeks to get up and running

Survey aimed for within 10 working days; installs at the survey where possible

toob

Not found on pages checked

At least 5 days between order and installation

Router sent a few days before

Rebel

Live within 5 days on an existing Openreach or CityFibre line

First engineer appointment usually around 14 days away

Can't bring a start date forward

Hey!Broadband

Not found on pages checked

Slots from 4 days after sign-up, availability permitting

Engineer visit of 1.5 to 2.5 hours

Truespeed

Not found on pages checked

Install of a new fibre line usually takes under an hour

Property assessed a week or two before; you needn't be in

V4 Consumer

Not found on pages checked

Its “Switching Timeline”: new router delivered Day 10, connected Day 14 with an engineer visit

Advertises a “2-Hours Installation Promise”

POP Telecom

Terms: around 10 working days on an existing compatible BT line

Terms: about 4 weeks for a new line

Go-live estimate within two days of ordering; usually up to 16 days in all

YouFibre

Not stated separately

When switching from another provider: up and running in 10 days, “or earlier if your diary is free”

Tells your old provider and switches you over on install day

Onestream

Not found on pages checked

Not found on pages checked

Confirms the activation date and whether an engineer is needed, usually within 72 hours

Virgin Media (home moves)

Self-install moves can be live in as little as 3 days

Engineer installs usually around 7-14 days

At least a day between old home off and new home on

BT (home moves)

Can take two weeks but often much faster

Not stated separately

New hub arrives a day before activation

Three (4G/5G hub)

Not applicable

No installation: hub delivered next working day

No engineer visit

TalkTalk

Not found on pages checked

Engineer details confirmed during the order; no days stated

New-build and converted homes can see delays

Vodafone

Not found on pages checked

Not found on pages checked

Late activation compensated automatically

A few things to keep in mind when reading it:

  • Working days and calendar days differ. Plusnet, Zen, Quickline, Airband and POP quote working days; ten working days is usually two weeks.
  • BT's and Virgin Media's figures come from their moving-home pages, so they describe moving an existing account to a new address rather than a brand-new order. (Virgin Media's moving page also says new customers can book installation up to 60 days before moving in, but gives no separate lead time for them.)
  • V4 Consumer's and YouFibre's figures are given for switching from another provider, which on their own networks still means an install visit.
  • Several providers publish no wait from order to installation. On the pages we checked for NOW, Community Fibre, Ogi, Zzoomm, Connect Fibre, Voneus, WightFibre and Rise Fibre we found how long the visit takes or how installation works, but no lead time in days. You'll need to ask.
  • Some give other timing details instead. Voneus says that if you're still in contract elsewhere it will hold your installation for up to 11 months. Connect Fibre takes pre-orders in some areas a few months before homes can be connected. Fibrus says that in Openreach areas your equipment arrives by Royal Mail up to 6 days before installation or activation.
  • A quick first date can still move if a survey finds outside work is needed.

Our guide to UK broadband providers links to a page on each one.

Why installations get delayed

Openreach says most full fibre installations go smoothly, but sometimes extra work is needed before you can be connected. The reasons it lists are:

  • Underground work: digging, or clearing blocked ducts (the underground pipes cables run through).
  • Tree cutting and work at height.
  • Road closures.
  • Water or debris in underground chambers or ducts.
  • Specialist engineers being needed.
  • Waiting for permissions, including wayleaves.

None of this is visible when you order, which is why a date can change after a survey. If yours is put back, ask your provider which reason applies and when the new date is. On Openreach's network, contact your provider first: Openreach says it can't see your order details and that the provider will contact it if needed.

Some delays start at home. Openreach says a decision maker over the age of 18 needs to be there throughout the appointment, and renters need the landlord's permission for drilling, so sort both out early. Delays the customer causes, such as not being home for an engineer visit, aren't covered by the automatic compensation scheme described below.

What happens on go-live day

"Go-live" is the day your new service is switched on. What it looks like depends on your situation.

Before go-live: when your router arrives

Engineer or not, your router or hub usually arrives a few days ahead. BT says a day before activation on a home move; POP about two days before go-live; Vodafone three days before your installation date; Onestream 3-5 days before go-live; toob a few days before installation (it needs the router to complete activation); and Fibrus up to 6 days before in Openreach areas. If it hasn't arrived a day or two before your date, chase the provider.

Don't cancel your old service too early

If you're switching provider at the same address through One Touch Switch, your old service runs until the new one is active, so don't cancel anything yourself first. Two exceptions to watch: One Touch Switch doesn't cover home moves (Rebel, for example, says home movers must cancel with their current provider themselves), and not every provider takes part. Connect Fibre, for instance, says it isn't part of One Touch Switch, so its customers cancel their old provider themselves after installation.

If no engineer is needed

EE and Sky both say you plug the hub in on your start date, with no engineer visit.

If an engineer is coming

  • Before the day: if an intruder alarm, health pendant or wrist alarm uses your phone line, Openreach says to contact your provider first.
  • Messages: Openreach publishes the numbers it texts from, for example 07701407770 (installing your new service) and 07491163160 (activating full fibre), and emails come from info@comms.openreach.co.uk. Checking Openreach's list helps you spot scam messages.
  • On arrival: the engineer calls or texts beforehand. Openreach advises checking their ID badge, and says it never asks for bank details.
  • During the visit: the engineer agrees the cable route with you, drills, fits the ONT and connects your router.
  • Afterwards: EE says that where an engineer visit is needed, the appointment date is when you go live. Once you're set up, run our broadband speed test.

If your start date slips: compensation and stop-gaps

Ofcom runs a voluntary automatic compensation scheme that started on 1 April 2019. Providers that have signed up pay set amounts without you having to claim, and the amounts rise each 1 April in line with inflation. ISPreview's April 2026 report of Ofcom's figures (Ofcom's own page wasn't reachable when we checked in October 2026) gives these amounts from April 2026:

What went wrong

Amount from April 2026

New service doesn't start on the agreed date

£6.46 per day of delay

Engineer misses an appointment

£32.31

Total loss of service not fixed within 2 working days

£10.34 per day

For comparison, the delayed-start payment was £5 a day when the scheme began in 2019. ISPreview lists the signatories as BT, EE, Plusnet, Hyperoptic, Sky (including NOW), TalkTalk, Utility Warehouse, Virgin Media, Vodafone and Zen, together covering about 97% of landline customers and 91% of broadband customers. Compensation can come as cash or a bill credit. Vodafone, for example, says late activation is compensated automatically. Our full guide to broadband automatic compensation explains the rules in detail.

If your provider isn't in the scheme, check its terms, and complain if a delay causes you problems: see how to complain about your broadband provider.

To stay online meanwhile, ask your provider what it offers. BT, for example, says that if it knows a home move will be delayed by more than two days it offers a 4G Mini Hub with unlimited EE data at no extra cost. Otherwise a phone hotspot or mobile broadband can tide you over: see our guide to setting up a backup broadband connection.

Planning your timing: a checklist

Before you order

  • Work out your situation. Is there a working line or fibre box? If you're moving, ask the seller, landlord or agent.
  • See who serves your address. Enter your postcode in the comparison on our broadband deals page to see the deals available there, or browse our broadband deals by area pages. If you want full fibre, our fibre broadband deals page shows fibre options for your postcode.
  • Use the results to plan around your deadline. If you have a fixed date to be online, such as a move-in day or the end of a contract, shortlist two or three providers from the comparison and look each one up in the table above. A provider quoting a short wait, or one that can switch on an existing connection remotely, may suit a tight deadline better than the cheapest deal. The comparison shows deals, not installation dates: the provider agrees your date when you order, so confirm it before you finish.
  • Ask the provider before you commit: Do I need an engineer? Is a survey likely? What's the earliest date you can offer, and is that in working days? Will my equipment arrive in time? Are you signed up to Ofcom's automatic compensation scheme?

If you're moving home

  • Start as soon as you have a completion or move-in date. BT says two weeks' notice is normally plenty for a home move, and Virgin Media's moving-home page says new customers can arrange installation up to 60 days before moving in.
  • Our guide to broadband when moving home walks through the whole process.

An example timeline

This is an illustration, not a prediction. Say you order full fibre from a provider quoting 6-20 working days, and a survey is needed. Expect the survey first, a confirmed install date after it, and go-live on installation day. If the survey finds a blocked duct, the date may move. Planning around the top of the stated range leaves room for that.

Broadband installation time FAQs

How long does it take to switch broadband if a line is already working?

Often days rather than weeks. Plusnet says existing full fibre is activated remotely, usually in 3 working days; Rebel says within 5 days on an existing Openreach or CityFibre line; Hyperoptic says minutes if its router and socket are already fitted. Under One Touch Switch your old service runs until the new one starts, and any loss of service should be no more than one working day where technically possible.

How long does a full fibre installation appointment take?

Openreach says most installations take between one and four hours, depending on the property and how the fibre is routed, and its checklist says around four hours. Other networks quote shorter visits: Gigaclear around 2 hours, Hyperoptic one to three hours, Hey!Broadband 1.5 to 2.5 hours and Truespeed usually under an hour.

Do I need to be at home for the installation?

For the installation itself, yes. Openreach says a decision maker over the age of 18 must be there throughout the whole appointment, and other providers including Plusnet, Hyperoptic and Trooli say an adult must be present. For an Openreach pre-visit you usually don't need to be in, though Openreach says that in a small number of cases, for example where it needs to check network behind a locked gate, it may contact you to arrange access, and someone over 18 must then be there. Truespeed says you needn't be home for its property assessment.

Can I contact Openreach directly to change my installation date?

Contact your provider first. Openreach says it doesn't have access to your order details, that your broadband provider manages the appointment and can resolve issues, and that the provider will get in touch with Openreach if needed. You can usually change the date by following the confirmation texts or emails you receive from your provider or Openreach, or by contacting your provider. Openreach publishes the numbers its messages come from, so you can check they're genuine.

Do I get compensation if my broadband isn't working on the agreed start date?

If your provider is in Ofcom's automatic compensation scheme, yes. ISPreview reports that from April 2026 signatories pay £6.46 for each day a new service starts late and £32.31 for a missed engineer appointment. Signatories include BT, EE, Plusnet, Sky, TalkTalk, Virgin Media, Vodafone and Zen. Delays you cause, such as not being home, aren't covered.

Why has my full fibre installation been delayed?

Openreach says common reasons include underground digging or blocked ducts, tree cutting, work at height, road closures, water or debris in chambers, the need for specialist engineers and waiting for permissions such as wayleaves. These usually only come to light after a survey. Ask your provider which applies and when the new date is.

How can I get online while I wait for installation?

A 4G or 5G hub is the usual stop-gap because nothing needs installing: Three, for example, delivers its hub the next working day. BT says it offers a 4G Mini Hub with unlimited EE data at no extra cost if a home move will be delayed by more than two days. A phone hotspot works for light use too.