Rural, 4G/5G & satellite

Project Gigabit: when will rural homes get fibre?

Project Gigabit: when will rural homes get fibre?

The honest answer to 'when?'

If full fibre still hasn't reached your village, hamlet or farm, you've probably heard that Project Gigabit is coming. The honest answer to 'when?' is that no national source gives a build date for an individual address. GOV.UK's contract pages say when the first premises in a contract were expected to be connected, not the last, and the list of addresses in each contract keeps changing.

What you can find out is whether your address is already covered, whether a provider plans to build there, whether you're inside a publicly funded contract, who holds it and how far it has got. Facts were checked in October 2026.

What is Project Gigabit?

Project Gigabit is the UK government's programme to bring gigabit-capable broadband to hard-to-reach homes and businesses that aren't in broadband companies' own commercial plans. The target is for 99% of UK premises to have access to a gigabit-capable connection by 2032.

'Gigabit-capable' means a wired connection that can deliver downloads of at least 1Gbps (1,000Mbps); government uses 'superfast' for over 30Mbps and 'ultrafast' for over 100Mbps. Full fibre, also called FTTP (fibre to the premises), where fibre runs all the way into your home, is one way to deliver it; GOV.UK notes that some providers use coaxial cable instead. Our guide to superfast, ultrafast and gigabit speeds explains the labels.

The 2020 Budget committed £5bn for the hardest-to-reach parts of the country through the schemes collectively known as Project Gigabit. It's run by Building Digital UK (BDUK), which moved into the Department for Digital, Culture, Media and Sport in July 2026; government says delivery plans are unchanged.

What it pays for, and what it doesn't

Project Gigabit doesn't sell you broadband or hand out cheap deals. It pays a subsidy to a network builder to lay wholesale infrastructure: the cables and ducts that broadband providers then use to sell services. Once the network is live you choose a provider and package in the normal way and pay for it like anyone else.

So the company that builds your network may not be the only one you can buy from, depending on which providers sell on that network. And you don't have to take the fastest package: GOV.UK points out that you can move onto full fibre and pay for a speed lower than 1Gbps.

Where things stand in 2026

BDUK's September 2026 progress update gives the latest official picture:

  • As of March 2026 the programme had helped bring gigabit-capable broadband to 1.4 million homes and businesses, with more than £2 billion committed through signed contracts.
  • Quoting Ofcom data for January 2026, BDUK says gigabit-capable broadband reached more than 88% of UK homes and businesses, up from 20% in May 2020, leaving roughly 4 million premises without it. Treat that as a January 2026 snapshot rather than today's figure.
  • Government says it can't yet say how many of those 4 million will need public money, and that the gaps are increasingly in towns, cities and built-up areas, although rural gaps remain.

How areas are chosen: Open Market Reviews and Public Reviews

Public money is only meant to go where the market won't build on its own. To find those places, BDUK asks network builders what they have and what they plan.

  • Open Market Review (OMR). A formal survey of suppliers. The National Rolling Open Market Review asks for premises-level information on what they've built and plan to build over the next three years, across the UK. It runs three times a year, in January, May and September.
  • Public Review. Before a local procurement, BDUK has also run a Public Review, in which the public, businesses, internet providers and network operators can submit evidence about existing or planned gigabit infrastructure.

Two things follow. If a company has told BDUK it plans to build to your address, you'll usually be left out of publicly funded plans, because subsidy is reserved for places with no credible commercial plan. And because BDUK reviews providers' plans every four months, eligibility moves: if a company changes or withdraws its plan, those premises can be considered for public support again.

New builds are a separate case. New homes in England are generally required to be built with gigabit-ready infrastructure and gigabit-capable connections, so they aren't generally part of Project Gigabit. See our guide to broadband in a new-build home.

How contracts are awarded

Once BDUK knows which premises have no commercial plan, it buys a build programme for them. The Scottish Government describes three routes: local (Type A), regional (Type B) and UK-wide framework (Type C) procurements. GOV.UK pages tend to say local, regional and cross-regional framework.

Local and regional contracts

These are the contracts you're most likely to hear about locally: a deal with a supplier to build to a defined list of premises, with BDUK working alongside the local council. For local contracts BDUK has used a dynamic purchasing system (DPS), an approved list of suppliers qualified to bid (its published supplier list was last updated in October 2024). GOV.UK publishes a summary page for each contract; at its December 2025 update the collection listed 36 pages, including some for contracts that have since ended.

The Openreach framework

In 2024 BDUK signed a cross-regional framework agreement with Openreach for hard-to-reach premises, mostly rural, where other suppliers had shown too little appetite, credibility or capacity to bid for smaller procurements. Work is ordered as 'call-off' contracts. GOV.UK listed eight in its 29 July 2026 update:

Call-off

Areas

Value

Premises

Awarded

1

Lancashire, West Berkshire, Staffordshire, Surrey, Hertfordshire, Wiltshire and Gloucestershire

£159.3m

60,180

June 2024

2

Devon, Mid Wales and South East Wales

£137.3m

41,140

June 2024

3

North Herefordshire, North Wales, Shropshire and South West Wales

£150.6m

65,120

Dec 2024

4

South Devon, Mid Devon and North Somerset

£77.1m

37,110

Dec 2024

5

Essex and North East England

£70.3m

35,300

Dec 2024

6

Rest of Scotland

£175.6m

77,640

April 2025

7

Worcestershire

£42.4m

22,980

Dec 2024

8

Cheshire

£37.5m

18,460

Feb 2026

More call-offs were being procured. For the remaining premises, BDUK said in September 2026 it would add them to nearby contracts already in delivery where practical (as it did for parts of Essex, Herefordshire and Shropshire in January to July 2026), run small local procurements, and use the framework where other routes aren't credible. It intends to finish framework awards by the end of 2027.

Openreach's customers are the communications providers that sell broadband to households, so where Openreach builds you order from one of those providers, not from Openreach itself; see what Openreach is and does.

Scotland, Wales and Northern Ireland

In Scotland the Scottish Government leads local and regional procurements (Scottish Borders and East Lothian in February 2025, North East Scotland in July 2025, with Orkney and Shetland, and Fife with parts of Perth and Kinross and Clackmannanshire, expected in 2026-27). In Northern Ireland the NI Executive is the contracting authority and awarded Fibrus a contract for over 9,000 premises in December 2025. In Wales, BDUK expects Openreach call-offs to reach around 60,000 premises. Ofcom figures quoted in BDUK's September 2026 update put gigabit coverage at 95% in Northern Ireland, 83% in Wales and 82% in Scotland. Our guide to the broadband rollout in Scotland and Northern Ireland covers those schemes.

Who is building it: contract examples

Many contracts have gone to regional full fibre builders, often called altnets (see what an altnet is). Figures are as reported at the date shown; scopes change.

Builder

Contract

What was reported

Quickline

North Yorkshire

£73.5m for around 36,300 premises, signed June 2024. Quickline also holds East Riding of Yorkshire and Lincolnshire (about 72,000 premises at award).

Gigaclear

Oxfordshire; East Gloucestershire

Two Oxfordshire contracts, £26.5m combined, around 10,000 premises, signed November 2023. East Gloucestershire scope rose by a net 325 premises, from 3,547 to 3,872, in September 2026.

Fibrus

Cumbria; Northern Ireland

Cumbria: £108.5m for up to 59,000 premises, signed 1 December 2022. Fibrus says it began with about 32,000 and added about 21,000 in March 2025. Northern Ireland: over 9,000 rural premises, December 2025.

Connect Fibre

Derbyshire

£33m for over 17,000 premises, signed November 2023. Scope raised to 18,651 in June 2026, then cut to 12,876 in July 2026.

GoFibre (Borderlink)

Teesdale

£6.6m, signed September 2022; build completed September 2025, around 4,400 homes and businesses able to connect.

CityFibre

Kent

£112m for around 50,000 premises, signed January 2024; redesigned in May 2026 to around 9,000 premises and £26.1m after commercial rollout in Kent expanded.

Sources: GOV.UK contract pages, BDUK data reported by ISPreview, and builders' own announcements. Every network we cover is on our broadband providers hub.

Why rural build takes years

Signing a contract is the start. GOV.UK's contract pages explain that build begins once the supplier has finished detailed plans, and that the preparatory work, digging trenches, laying duct and installing fibre, varies by geography and supplier. BDUK also names common barriers: access to land, wayleaves (legal permission to run cables over or under private land), planning constraints and access to blocks of flats. Our guides to broadband wayleaves and full fibre in flats explain those.

The pace varies. Teesdale was signed in September 2022 and finished in September 2025. In Derbyshire, a contract signed in November 2023 had completed build for 1,200 premises by June 2026, according to BDUK data reported by ISPreview. In Quickline's Lincolnshire and East Riding contract, June 2026 data showed 20,610 premises covered out of 47,800 contracted. None of this dates your street, but contracts run for years. BDUK publishes monthly premises contracted and built for each contract if you want to follow progress.

What 'in scope' really means for your address

'In scope' means your address is on the list of premises a contract is meant to reach. It's good news, but not a promise or a date. GOV.UK's contract pages say the premises to be reached are subject to change, for example if another provider has already connected them, after detailed planning, or because of extraordinary engineering difficulties.

Initial scope and deferred scope

Initial scope is the set of premises the builder is contracted to reach. Deferred scope, as ISPreview explains it, typically covers premises where BDUK was waiting to see whether other operators' commercial plans or voucher projects turned into real build. They might be added later, or they might not.

Why addresses get added or removed

  • Someone else is building. In May 2026, after commercial rollout in Kent expanded significantly, CityFibre's Kent contract was redesigned from around 50,000 premises to around 9,000 to minimise overlap with other suppliers' commercial rollout. BDUK is talking to other suppliers about premises left out of every plan.
  • Deferred premises dropped. In June 2026 BDUK removed a net 828 initial-scope and 28,187 deferred-scope premises from Quickline's Lincolnshire and East Riding contract.
  • Up, then down. Connect Fibre's Derbyshire scope rose to 18,651 in June 2026 and was cut to 12,876 a month later, after an Open Market Review.
  • Added and removed at once. In September 2026 Gigaclear's East Gloucestershire contract gained 912 premises and lost 587, a net increase of 325, while its value fell by £777,041.

There's no single reason for a removal. One common reason is that another company has told BDUK it will build there commercially; GOV.UK's contract pages say scope can also change after the builder's detailed planning or for technical reasons, and some premises are left out because of cost or difficulty. Commercial plans can change too, which is why the reviews keep running.

Reasons your address isn't in any contract

GOV.UK's contract pages list the usual reasons:

  1. Gigabit-capable infrastructure is already there.
  2. A supplier declared commercial plans in the Open Market Review or Public Review, which can include voucher projects.
  3. It's part of another Project Gigabit contract or another subsidy scheme.
  4. It's out of scope because of cost or difficulty, known as 'Very Hard to Reach'.

Very Hard to Reach premises

Government expects a small proportion of premises to stay too difficult or costly to include. It will assess them separately and keep watching fixed wireless and satellite, which it says already make ultrafast (100Mbps+) speeds widely available, and it expects more satellite options in 2026 to 2027. See our guides to rural broadband options, fixed wireless broadband and satellite broadband, and to the broadband Universal Service Obligation, a separate scheme from Project Gigabit.

How to check where your address stands

Work through these in order. Our guide on how to check full fibre availability covers each tool in more depth.

  1. Use the GOV.UK checker (England and Wales only). The gigabit availability checker shows whether gigabit broadband is available, planned, or not in known plans for your address. As of its 6 October 2026 update it uses May 2026 Open Market Review data, with the next update due in February 2027 and every four months after. GOV.UK can't guarantee complete accuracy, so treat it as a strong guide.
  2. In Scotland or Northern Ireland, use the Scottish Government's broadband checker or the Northern Ireland Project Gigabit checker.
  3. If you're in a contract, read its contract page for the supplier and area, then check the monthly contracted-and-built figures.
  4. Check the builder's website for your address, which is where you'll see whether ordering has opened.
  5. See what's on sale now. Enter your postcode in the comparison on our fibre broadband deals page, then confirm your exact address with the provider before ordering.

Worth asking the network builder: has detailed planning for my area been done; is my address in initial or deferred scope; is anything such as a wayleave holding up my road; and will you tell me when I can order? If your neighbours have fibre and you don't, our guide to when full fibre isn't in your street covers the likely reasons.

When the network arrives: you still have to order

Nothing changes at your home until you order. GOV.UK's contract pages say residents and businesses need to request a connection from a broadband service provider once the network is built; your existing service doesn't switch over by itself.

  • Compare first. Put your postcode into the comparison on our fibre broadband deals page to see deals across providers. If you know your builder, our Gigaclear, Fibrus, Connect Fibre and Quickline pages show that provider's own deals. We compare deals through a partner widget; we don't switch you ourselves.
  • Don't overbuy speed. Pick what your household needs; our guide to what broadband speed you need helps.
  • Check your current contract. Look at your contract summary for the end date and any exit charges before ordering.
  • Expect an engineer visit. Full fibre needs an engineer to install; our guide to upgrading to full fibre explains the steps.

GOV.UK also says older ADSL broadband will be phased out by 31 January 2027 as the old phone network is retired, so if you're on ADSL, check what your provider plans to move you to.

If a contract falls through

Occasionally a contract ends early, and BDUK finds another route. Two examples from GOV.UK:

  • Derbyshire Peak District. BDUK and FullFibre agreed to end the contract (in 2025, according to BDUK's September 2026 update). In April 2026 BDUK added the area to Openreach call-off 1, which covers parts of Staffordshire.
  • Mid West Shropshire. BDUK and Voneus mutually agreed to end the contract, and Voneus received no public funding for it. In October 2025 the premises were added to Openreach call-off 3, which covers other parts of Shropshire.

Either way, expect a longer wait. Keep an eye on the address checker and the new contract's monthly figures.

Gigabit vouchers: closed to new projects

Alongside the big contracts, Project Gigabit ran the Gigabit Broadband Voucher Scheme (GBVS): vouchers worth up to £4,500 per eligible premises, which registered suppliers pooled to build to a group of homes or businesses where there was no Project Gigabit contract and no existing or planned commercial coverage. Voneus and WightFibre were among the registered voucher suppliers. BDUK says more than 28,000 premises in Wales got gigabit-capable connections through voucher-funded delivery.

From GOV.UK's scheme page (updated 2 September 2026):

  • The scheme closed to new voucher projects on 31 August 2026, and new supplier registrations are no longer accepted.
  • Existing projects continue until the planned closure on 31 March 2028, or an earlier agreed end date, and vouchers must be issued before March 2027 unless another date is agreed.
  • Projects needed at least two eligible premises, and the new connection had to at least double speeds below 50Mbps, or reach at least 100Mbps where speeds were above 50Mbps.
  • The supplier is paid only once your home is connected; you'll be asked to confirm the connection works, and BDUK may audit installations.

For questions about an existing project, GOV.UK says to contact the supplier. Full details are on the voucher scheme information page.

While you wait

  • Test what you have. Run our broadband speed test at a few times of day so you know your real speeds.
  • Look at stopgaps. Fixed wireless, 4G or 5G home broadband and satellite can fill the gap; see whether 4G or 5G can replace fixed broadband.
  • Avoid long lock-ins. If you take a stopgap, check the minimum term so you aren't stuck when fibre arrives. A rolling monthly contract can be a sensible bridge.
  • Keep checking. The GOV.UK checker is updated every four months, with a lag (May 2026 review data appeared in September 2026), and our broadband deals by area pages show deals where you live.

Project Gigabit FAQs

When will Project Gigabit reach my village?

No national source gives a build date for a single address. Contract pages only say when the first premises were expected, and scopes change. Use the GOV.UK checker (England and Wales), read your contract page, follow the monthly contracted-and-built figures and check the builder's website.

My address is 'in scope'. Does that mean I'll definitely get full fibre?

No. In scope means you're on a contract's list, but GOV.UK says the premises to be reached can change, for example if another provider connects them first, after detailed planning, or because of serious engineering difficulties. Deferred-scope premises are less certain still.

Why was my address removed from a Project Gigabit contract?

There's no single reason. One common reason is that another company has declared commercial build plans there, often through an Open Market Review, so public money isn't needed. Scope can also change after the builder's detailed planning, for technical reasons, or because of cost. If commercial plans later fall through, those premises can be considered for support again.

Do I get full fibre automatically once the network is built?

No. GOV.UK's contract pages say residents and businesses need to request a connection from a broadband provider once the network is built. Compare deals at your postcode, check your current contract's end date and exit charges, then order. An engineer will need to install it.

Can I still apply for a gigabit broadband voucher?

Not for a new project. The Gigabit Broadband Voucher Scheme closed to new voucher projects on 31 August 2026. Existing projects carry on until 31 March 2028 or their agreed end date. If you're in an existing project, ask the supplier running it.

What happens if the company building my area pulls out?

BDUK looks for another way to reach those premises, often by adding them to a nearby contract. After the Derbyshire Peak District contract ended, the area joined Openreach call-off 1 in April 2026; Mid West Shropshire's premises joined Openreach call-off 3 in October 2025. Expect a longer wait.

Does Project Gigabit cover new-build homes?

Generally not. New homes in England are generally required to be built with gigabit-ready infrastructure and gigabit-capable connections, so government says new builds aren't generally in scope. If you're moving into one, ask the developer which network has been installed.

Ready to compare deals at your address?